Gui'an T4 Cloud Base
The building has a total area of 5200M2 and consists of two floors. The first floor is dedicated to the generator room and fuel room; The second floor is for high-voltage distribution room, control room, etc. Construct 4 sets of high-voltage switching systems (2 sets per building) and 1 set of generator parallel system. Six 10KV main power 1800KW diesel generator sets, four 3m3 daily fuel tanks, and two 30m3 underground fuel tanks will be built on the first floor.
★ A3 machine building: Power distribution system 2N mode.
★ A4 machine building: Power distribution system 2N mode.
★ A5 machine building: Power distribution system 2N mode.
★ A6 machine building: 2N mode of power distribution system.